A status conference was held Aug. 29 between Macomb Township and the owners of the Tina's properties on North Avenue regarding a breach in the pair's January 2011 consent judgment.

A Macomb County Circuit Court judge has ordered the owners of and to build a southbound bypass lane opposite their property on North Avenue by Sept. 24 or face legal consequences, according to court documents.

Judge James Biernat, Jr. issued the order Wednesday morning following a status conference between the parties involved in the case of .

This conference was held to address a breach in the signed by owners of the Tina’s properties (TTCH Development) and Macomb Township following some three years of legal disputes. Per the consent judgment, Tina’s owners, sisters Cathy and Mary Jo Imbronone, had until June 1 to build a bypass lane on the west side of North Avenue.

Interested in local real estate?Subscribe to Patch's new newsletter to be the first to know about open houses, new listings and more.

When the deadline passed and the work was not completed, Macomb Township's legal counsel asked the court to hold TTCH Development in comtempt of court and costs. The judge agreed to give TTCH Development until Sept. 24 at 11 a.m. to engage a contractor to perform the work as described in plans approved by the Macomb County Department of Roads (i.e. a southbound bypass lane on North Avenue south of 23 Mile Road).

Should the bypass lane not be completed on or before Sept. 24, the judge ordered TTCH Development to immediately contact the court with an updated report.

Interested in local real estate?Subscribe to Patch's new newsletter to be the first to know about open houses, new listings and more.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here